Kargow-Schlön substation: double connection with 2x 40/50 MVA

Two 40/50 MVA transformers, Hypact technology and forward-looking BESS preparation: we coordinated planning, delivery and construction so seamlessly that the plant was handed over on schedule and in the required quality despite tight deadlines.

2x 40/50 MVA
More flexibility, reduced risk of downtime
Nature reserve
Eco-friendly construction & fully compliant with permitting requirements
On schedule
Completed intrayear – delivered on plan

Transformer station for two photovoltaic parks (Kargow & Schlön)

As part of an EPC project, we built a new substation as a double-busbar system with two 40/50 MVA transformers. The substation feeds electricity from the Kargow and Schlön PV parks; the integration of a future battery storage system has already been planned. Despite a tight schedule and the environmental restrictions of a nature reserve, we successfully handed over the plant on time and in the required quality.

At a glance
  • 2× 40/50 MVA into the 110 kV grid: transformers for maximum operational flexibility
  • Two PV parks connected: Schlön in operation, Kargow shortly before construction start
  • BESS-ready: substation and protection concept designed for future battery storage integration
  • Construction in nature reserve: permit-compliant, environmentally friendly construction methods and careful logistics
  • Hypact switchgear integrated: compact technology for fast installation and small footprint
  • On schedule & intrayear: completed during the year – handover as planned

Aim of the project

  • Construction of a substation as a double-ended substation with two 40/50 MVA transformers
  • Grid-side feed-in from the Kargow and Schlön PV parks
  • Preparation for battery storage (areas, cable routes, protection and control technology conceptually taken into account)
Key challenges
  • Location in a nature reserve: strict environmental and building regulations
  • Safety: modern protection and control technology, occupational safety on the construction site
  • New technology: Integration of Hypact compact fields and BESS preparation
  • Tight schedule & construction during the year: limited weather and closure windows
‘The team coordinated planning, delivery and construction so effectively that we were able to stay on schedule despite sensitive constraints in the nature reserve.’
Laura, Management

Project milestones

  • Completion of civil engineering works
  • Completion of switchgear building
  • Delivery of Hypact fields
  • Delivery of transformers
  • Delivery of MV system
  • Commissioning of substation
  • Handover to operator

Technical planning and coordination

  • Complete in-house planning: primary/secondary technology, protection, control technology, BESS preparation
  • Monitoring of all construction work (civil engineering, steel construction, cable routes, earthing)
  • Delivery and installation of main components, including Hypact fields and transformers
  • Quality and function: protection testing, commissioning, documentation
  • Partner management: clear interfaces, construction meetings, approvals
  • Communication hub: central coordination of all project participants
  • Schedule and cost control: transparency regarding progress and budget
Challenges & Solutions
  • Schedule risks addressed early on -> rescheduling of construction phases, parallelisation of trades
  • Additional services (supplementary offer) covered transparently -> clear scope definition
  • Nature conservation requirements complied with -> careful logistics, soil protection, ecological construction supervision

Results

  • On schedule: handover within the planned time frame
  • Quality assured: complete testing and acceptance documentation
  • Future-proof: substation BESS-ready, flexible operation management thanks to 40/50 MVA transformers
  • High plant availability: modern protection and control technology, compact switchgear

Summary

This project demonstrates our strength in implementing sophisticated energy infrastructure on schedule and with quality assurance – even in nature reserves. With the construction of a new substation as a double-ended connection and two 40/50 MVA transformers, we have ensured the feed-in of the Kargow and Schlön PV parks and designed the plant to be BESS-ready. The handover took place on schedule, with documented functionality, high availability and clear prospects for further expansion.